When a scheduled sub-task is due, clicking on "Add to today" should result in tagging the whole task including the sub-task with "today".
When a scheduled sub-task is due, clicking on "Add to today" results in it is added as a singular main task without option to be moved again – but it also remains a sub-task. Both tasks seem to be the same, time tracking applies to both, if you delete one, both are gone (see screenshots). Task can't be moved in list position by drag and drop either.


Hi Gunnar! Thank you for reporting. I try to provide a fix with the next release!
The fix should be available starting with version 4.0.0 (currently only available as pre release).